How to Plan a Geotechnical Site Investigation

A geotechnical site investigation begins with the decisions the design must support.

Indonesian version

A geotechnical site investigation begins with the decisions the design must support. Boreholes for bridge foundations and soundings along an approach embankment answer different questions. Collect historic maps, land-use records and previous reports before selecting test locations.

Target the uncertainty that matters

A former stream channel crossing a road alignment may contain soft or loose material between widely spaced explorations. Use targeted soundings to trace the channel, then sample representative layers for laboratory testing. Size the depth and spacing of the program to the structural loads, excavation levels and geological variability. Schedule groundwater observations early enough to capture recovery after drilling and identify where seasonal readings would change the design.

Example investigation for a road embankment

Consider a 4 m embankment across an alluvial plain. Desk records show a former channel, but three earlier borings were on its margins. Place a transverse line of CPT soundings to locate the channel and add a boring near its deepest interpreted point to sample any soft clay. Request consolidation testing to estimate settlement under the proposed fill and appropriate strength tests for rapid loading. Use piezometers to separate shallow groundwater from pressure in deeper lenses where relevant. The investigation should establish whether the channel warrants a distinct foundation treatment or a different loading sequence.

How deep should an investigation go?

Depth should reach layers capable of influencing the intended structure or excavation, including deeper weak or compressible horizons where the ground model indicates them.